one draycott

1 Draycott Park, District 10
SITE PROGRESS
Site Photos
March 2023

End March 2023
Construction completed. TOP obtained on 18 April 2023.

March 2023

End March 2023
Construction completed. Expecting TOP in April 2023.

February Side 2023

End February 2023 (Front)
All finishing works are in progress. The estimated TOP is March / April 2023.

February 2023

End February 2023 (Side)
All finishing works are in progress. The estimated TOP is March / April 2023.

February 2023

End February 2023
All finishing works are in progress. The estimated TOP is March / April 2023.

January Elevation 2023

End January 2023 (Elevation)
All finishing works are in progress. The estimated TOP is March / April 2023.

January 2023

End January 2023
All finishing works are in progress. The estimated TOP is March / April 2023.

December Elevation 2022

End December 2022 (Elevation)
All finishing works are in progress. The estimated TOP is in Q1 2023.

December 2022

End December 2022
All finishing works are in progress. The estimated TOP is in Q1 2023.

November Elevation 2022

End November 2022 (Elevation)
Internal finishing work in progress and roof top crown feature installation in progress.

November 2022

End November 2022
Internal finishing work in progress and roof top crown feature installation in progress.

October Elevation 2022

End October 2022 (Elevation)
All finishing works are in progress.

October 2022

End October 2022
All finishing works are in progress.

September Elevation 2022

End September 2022 (Elevation)
All finishing works are in progress.

September 2022

End September 2022
All finishing works are in progress.

August Elevation 2022

End August 2022 (Elevation)
Architectural and M&E finishes are in progress at basement and typical floor units.

August 2022

End August 2022
Architectural and M&E finishes are in progress at basement and typical floor units.

July Elevation 2022

End July 2022 (Elevation)
Architectural and M&E finishes are in progress at basement and typical floor units.

July 2022

End July 2022
Architectural and M&E finishes are in progress at basement and typical floor units..

Lorem ipsum

End June 2022 (Side View)
Architectural and M&E finishes are in progress at basement and typical floor units.

Lorem ipsum

End June 2022 (Front View)
Architectural and M&E finishes are in progress at basement and typical floor units.

Lorem ipsum

End May 2022 (Elevation)
Architectural and M&E finishes are in progress at basement and typical floor units.

Lorem ipsum

End May 2022
Architectural and M&E finishes are in progress at basement and typical floor units.

Lorem ipsum

End April 2022 (Elevation)
Architectural and M&E finishes are in progress at basement and typical floor units.

Lorem ipsum

End April 2022
Architectural and M&E finishes are in progress at basement and typical floor units.

Lorem ipsum

End March 2022 (Elevation)
Architectural and M&E finishes are in progress at basement and typical floor units.

Lorem ipsum

End March 2022
Architectural and M&E finishes are in progress at basement and typical floor units.

Lorem ipsum

End February 2022 (Elevation)
The roof structural slab is completed. Architectural and M&E finishes are in progress at lower floor units.

Lorem ipsum

End February 2022
The roof structural slab is completed. Architectural and M&E finishes are in progress at lower floor units.

Lorem ipsum

End January 2022 (Elevation)
The roof structural slab is in progress. Architectural finishes in progress at level 3-11.

Lorem ipsum

End January 2022
The roof structural slab is in progress. Architectural finishes in progress at level 3-11.

Lorem ipsum

End December 2021 (Elevation)
The level 18 structural slab is in progress. Architectural finishes in progress at level 3-10.

Lorem ipsum

End December 2021
The level 18 structural slab is in progress. Architectural finishes in progress at level 3-10.

Lorem ipsum

End November 2021 (Elevation)
The level 13 structural slab is in progress. Architectural finishing in progress at level 3 and 4.

Lorem ipsum

End November 2021
The level 15 structural slab is completed, in progress to level 16. Architectural finishes in progress at level 3-7.

Lorem ipsum

End October 2021 (Elevation)
The level 13 structural slab is in progress. Architectural finishing in progress at level 3 and 4.

Lorem ipsum

End October 2021
The level 13 structural slab is in progress. Architectural finishing in progress at level 3 and 4.

Lorem ipsum

End September 2021 (Elevation)
The level 11 structural slab is in progress. Architectural finishing in progress at level 3.

Lorem ipsum

End September 2021
The level 11 structural slab is in progress. Architectural finishing in progress at level 3.

Lorem ipsum

End August 2021 (Elevation)
The level 8 structural slab is completed, level 9 structural slab is in progress.

Lorem ipsum

End August 2021
The level 8 structural slab is completed, level 9 structural slab is in progress.

Lorem ipsum

End July 2021 (Elevation)
The level 6 structural slab is in progress.

Lorem ipsum

End July 2021
The level 6 structural slab is in progress.

Lorem ipsum

End June 2021 (Elevation)
The level 4 structural transfer slab is in progress.

Lorem ipsum

End June 2021
The level 4 structural transfer slab is in progress.

Lorem ipsum

End May 2021 (Elevation)
The level 3 structural transfer slab is in progress.

Lorem ipsum

End May 2021
The level 3 structural transfer slab is in progress.

Lorem ipsum

End April 2021 (Elevation)
The progress of level 2 structural slab is completed. In progress to level 3.

Lorem ipsum

End April 2021
The progress of level 2 structural slab is completed. In progress to level 3.

Lorem ipsum

End March 2021 (Elevation)
The progress is going up to level 2 structural slab.

Lorem ipsum

End March 2021
The progress is going up to level 2 structural slab.

Lorem ipsum

End February 2021 (Elevation)
The progress is going up to level 2 structural slab.

Lorem ipsum

End February 2021
The progress is going up to level 2 structural slab.

Lorem ipsum

End January 2021 (Elevation)
The progress is going up to level 2 structural slab.

Lorem ipsum

End January 2021
The progress is going up to level 2 structural slab.

Lorem ipsum

End December 2020 (Elevation)
The architectural and M&E works in progress.

Lorem ipsum

End December 2020
The architectural and M&E works in progress.

Lorem ipsum

End November 2020 (Side View)
The architectural and M&E works in progress.

Lorem ipsum

End November 2020
The architectural and M&E works in progress.

Lorem ipsum

End October 2020 (Elevation)
The architectural and M&E works in progress.

Lorem ipsum

End October 2020
The architectural and M&E works in progress.

Lorem ipsum

End August 2020 (Elevation)
The architectural and M&E works in progress.

Lorem ipsum

End August 2020
The architectural and M&E works in progress.

Lorem ipsum

End July 2020
The architectural and M&E works in progress.

Lorem ipsum

End June 2020
The architectural and M&E works in progress.

Lorem ipsum

End March 2020 (Elevation)
The architectural and M&E works in progress.

Lorem ipsum

End March 2020
The architectural and M&E works in progress.

Lorem ipsum

End February 2020
The architectural and M&E works in progress.

Lorem ipsum

End December 2019 (Elevation)
The architectural and M&E works in progress.

Lorem ipsum

End December 2019
The architectural and M&E works in progress.

Lorem ipsum

End November 2019
The architectural and M&E works in progress.

Lorem ipsum

End November 2019
The architectural and M&E works in progress.

Lorem ipsum

End October 2019
The architectural and M&E works in progress.

Lorem ipsum

End October 2019
The architectural and M&E works in progress.

Lorem ipsum

End September 2019
The architectural and M&E works are in progress.

Lorem ipsum

End August 2019
Ground works in progress.

Lorem ipsum

End June 2019
Ground works in progress.

Lorem ipsum

End April 2019
Ground works in progress.

Lorem ipsum

End March 2019
Ground works in progress.

Lorem ipsum

End February 2019
Ground works in progress.

Lorem ipsum

End January 2019
Ground works in progress.

Lorem ipsum

End December 2018
Ground works in progress.

Lorem ipsum

End November 2018
Ground works in progress.

Ooops!
Generic Popup2