MYRA

Meyappa Chettiar Road, District 13
SITE PROGRESS
Site Photos

End March 2024
The site had completed the works, pending authorities clearances for TOP. Target to obtain TOP in April 2024.

End March 2024
The site had completed the works, pending authorities clearances for TOP. Target to obtain TOP in April 2024.

End February 2024
The site had completed the works, pending authorities clearances for TOP. Target to obtain TOP in March/April 2024.

End February 2024
The site had completed the works, pending authorities clearances for TOP. Target to obtain TOP in March/April 2024.

End January 2024
The site had completed the works, pending authorities clearances for TOP. Target to obtain TOP in March/April 2024.

End January 2024
The site had completed the works, pending authorities clearances for TOP. Target to obtain TOP in March/April 2024.

End December 2023
The architectural, M&E and landscape works are all in progress. External boundary wall in progress. Target to obtain TOP in March/April 2024.

End December 2023
The architectural, M&E and landscape works are all in progress. External boundary wall in progress. Target to obtain TOP in March/April 2024.

End November 2023
The architectural, M&E and landscape works are all in progress. External boundary wall in progress. Target to obtain TOP in 1H 2024.

End November 2023
The architectural, M&E and landscape works are all in progress. External boundary wall in progress. Target to obtain TOP in 1H 2024.

End October 2023
The architectural, M&E and landscape works are all in progress. Target to obtain TOP in 1H 2024.

End October 2023
The architectural, M&E and landscape works are all in progress. Target to obtain TOP in 1H 2024.

End September 2023
The tower crane has been removed, and the architectural and M&E works are in progress at lower levels. Target to obtain TOP in 1H 2024.

End September 2023
The tower crane has been removed, and the architectural and M&E works are in progress at lower levels. Target to obtain TOP in 1H 2024.

End August 2023
The structural roof slab is completed, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.

End August 2023
The structural roof slab is completed, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.

End July 2023
The structural roof slab is completed, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.

End July 2023
The structural roof slab is completed, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.

End June 2023
The structural slab is in progress at roof level, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.

End June 2023
The structural slab is in progress at roof level, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.

End May 2023
The structural slab is in progress at level 11, and the architectural and M&E works are at level 2- level 5. Target to obtain TOP in 1H 2024.

End May 2023
The structural slab is in progress at level 11, and the architectural and M&E works are at level 2- level 5. Target to obtain TOP in 1H 2024.

End April 2023
Level 10 structural slab is in progress. Lower floors architectural and M&E are in progress.

End April 2023
Level 10 structural slab is in progress. Lower floors architectural and M&E are in progress.

End March 2023
The basement construction works is completed. Level 8 structural slab is in progress.

End March 2023
The basement construction works is completed. Level 8 structural slab is in progress.

End February 2023
The basement construction works is about 97% completed. Level 6 structural slab is in progress.

End February 2023
The basement construction works is about 97% completed. Level 6 structural slab is in progress.

End January 2023
The basement construction works is about 95% completed. Level 4 structural slab is in progress.

End January 2023
The basement construction works is about 95% completed. Level 4 structural slab is in progress.

End December 2022
The basement excavation about 95% completed. Level 2 structural slab completed. Level 3 structural slab in progress.

End December 2022
The basement excavation about 95% completed. Level 2 structural slab completed. Level 3 structural slab in progress.

End November 2022
Level 1 slab 80% completed, Level 2 slab 50% completed.

End November 2022
Level 1 slab 80% completed, Level 2 slab 50% completed.

End October 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.

End October 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.

End September 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.

End September 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.

End August 2022
The basement excavation is in progress and is about 90% completed. Slab in progress to level 1.

End August 2022
The basement excavation is in progress and is about 90% completed. Slab in progress to level 1.

End July 2022
The basement excavation is in progress and is about 85% completed. Slab in progress to level 1.

End July 2022
The basement excavation is in progress and is about 85% completed. Slab in progress to level 1.

Lorem ipsum

End June 2022
The basement excavation is in progress and is about 80% completed.

Lorem ipsum

End June 2022
The basement excavation is in progress and is about 80% completed.

Lorem ipsum

End May 2022
The basement excavation is in progress and is about 50% completed.

Lorem ipsum

End May 2022
The basement excavation is in progress and is about 50% completed.

Lorem ipsum

End April 2022
The basement excavation is in progress and is about 35% completed.

Lorem ipsum

End April 2022
The basement excavation is in progress and is about 35% completed.

Lorem ipsum

End March 2022
The basement excavation is in progress and is about 30% completed.

Lorem ipsum

End March 2022
The basement excavation is in progress and is about 30% completed.

Lorem ipsum

End February 2022
The piling is completed, and the excavation to basement had commenced.

Lorem ipsum

End February 2022
The piling work is completed and excavation to basement had commenced.

Lorem ipsum

End January 2022
The contractor is doing piling works, about 90% completed.

Lorem ipsum

End January 2022
The contractor is doing piling work, about 90% completed.

Lorem ipsum

End December 2021
The contractor is doing piling works, about 90% completed.

Lorem ipsum

End December 2021
The contractor is doing piling work, about 90% completed.

Lorem ipsum

End November 2021
The contractor is doing piling works, about 65% completed.

Lorem ipsum

End November 2021
The contractor is doing piling work, about 65% completed.

Lorem ipsum

End October 2021
The contractor is doing piling, about 40% completed.

Lorem ipsum

End October 2021
The contractor is doing piling, about 40% completed.

Lorem ipsum

End September 2021
Ground works in progress and the contractor is doing soil improvement piles.

Lorem ipsum

End September 2021
Ground works in progress and the contractor is doing soil improvement piles.

Lorem ipsum

End August 2021
Ground works in progress and the contractor is doing site setup.

Lorem ipsum

End August 2021
Ground works in progress and the contractor is doing site setup.

Lorem ipsum

End June 2021
Ground works in progress and the contractor is doing site setup.

Lorem ipsum

End June 2021
Ground works in progress and the contractor is doing site setup.

Lorem ipsum

End December 2020
Ground works in progress.