End May 2021
The architectural and M&E finishing works are on-going at all floors of the residential building and conserved building. The external roadworks along Serangoon Road and the construction of the Park Connector beside Kallang River is completed. Target TOP by 3Q/4Q 2021.
End March 2021
The architectural and M&E works are on-going at all floors, level 5 recreation floor finishes in progress. The external roadworks along Serangoon Road and the construction of the Park Connector beside Kallang River is in progress. Existing conserved building architectural works in progress. TOP at 3Q/4Q 2021.
End January 2021
The architectural and M&E works are on-going at all floors, swimming pool tiling installation in progress. The external roadworks along Serangoon Road and the construction of the Park Connector beside Kallang River is in progress. TOP at 3Q/4Q 2021.
End October 2020
The architectural and M&E works are on-going at all floors in progress. The external roadworks along Serangoon Road and the construction of the Park Connector beside Kallang River is in progress. TOP at 3Q/4Q 2021.
End July 2020
The architectural and M&E works are on-going at all floors in progress. The external roadworks along Serangoon Road and the construction of the Park Connector beside Kallang River is in progress. TOP at 3Q/4Q 2021.
End June 2020
The architectural and M&E works are on-going at all floors in progress. The external roadworks along Serangoon Road and the construction of the Park Connector beside Kallang River is in progress. TOP at 3Q/4Q 2021.
End November 2019
The architectural and M&E works are on-going at all floors in progress. TOP at 3Q/4Q 2021.
End October 2019
The architectural and M&E works are on-going at all floors in progress. TOP at 3Q/4Q 2021.
End September 2019
The architectural and M&E works are on-going at all floors in progress. TOP at 3Q/4Q 2021.